Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
can't understand your question click a clear pic of your question
Answer:
Step-by-step explanation:
36x^3 - 81x
9x(4x^2 - 9)
9x(2x - 3)(2x + 3)
She is right
Answer:
3160
Step-by-step explanation:
3.16 x 10^3
10^3 = 1000
so you move the decimal point three times to the right
I hope this helps