<span>This is a true or false question that often shows up on business related tests. The answer: true. Bosses who micromanage things often have employees who are frustrated and unhappy. In many cases, they feel undervalued and that they are not trusted to handle tasks without direct supervision from the boss. Companies that have a boss who is a micro-manager usually have a high turnover rate.</span>
Answer:
Investment in stock C is $122450.3311 rounded off to $122450.33
Explanation:
A portfolio which is equally as risky as market should have a beta equal to the beta of the market as beta is a measure of the riskiness. The beta of market is always equal to 1. The formula for beta of a portfolio is as follows:
Portfolio beta = wA * Beta A + wB * Beta B + ... + wN * Beta N
Where w represents the weight of each stock in the portfolio.
Let investment in stock C be x
1 = 146000/500000 * 0.91 + 134000/500000 * 1.36 + x/500000 * 1.51
1 = 0.26572 + 0.36448 + 1.51x / 500000
1 - 0.6302 = 1.51x / 500000
0.3698 * 500000 = 1.51x
1844900 / 1.51 = x
x = $122450.3311 rounded off to $122450.33
The booking process.
I hope this helps and have a good night! :D
If a coconut is a normal good and the price of coconuts increases, then the movement that would take place in the model could be B to A.
<h3>What happens when prices rise?</h3><h3 />
For Normal goods, a rise in prices would mean a fall in the quantity demanded. This is shown by the demand curve which shows the relationship between the quantity demanded and price.
When there is a price change, the movement will be along the demand curve which means that the demand curve would see a movement from Point B to Point A for coconuts.
Find out more on price changes and the demand curve at brainly.com/question/1139186
#SPJ1
Answer:
22 days
Explanation:
number of activities : 3 ( A,B,C)
connected via : SS and FF combination. days lag on SS and F = 2
Durations : 5,10 and 3
A and B is connected by SS and there is a 2-day lag on the SS connection, this means that B will start 2 days after A have ended
i.e when T = 0 , B will start : 5 +2 = 7 days and end in 17 days
while B and C is connected by FF and there is also a 2-day lag on the FF connection, this means that C will start after B has ended and end in 2 days
i.e when B ends at 17 days ; C starts = 17 + 2 = 19 DAYS
hence the project will end in 19 + 3 = 22 days ( i.e when C ends )