Answer:
On average, the project takes 4 weeks to complete.
Step-by-step explanation:
We have these following probabilities:
25% probability that the activity takes 2 weeks.
50% probability that the activity takes 4 weeks.
25% probability that the activity takes 6 weeks.
How long does the project now take to complete (on average)
We multiply each duration by it's probability.
0.25*2 + 0.5*4 + 0.25*6 = 4
On average, the project takes 4 weeks to complete.
Answer: 36b
Step-by-step explanation:
3•3=9 add the 9
9b • 4
<span>The coordinate notation is (x,y)---- >(x+1,y-2)</span>
<span>Q(-2, 8)
only y coordinate is (y)--------------- > ( y-2)
therefore
(8)------------------------------------ >(8-2)=(6)
the y coordinate </span><span>
of Q' is 6</span>
Answer:
or 
Step-by-step explanation:
Assuming the question to be finding the value of b.
Solution:
Rewrite the equation as.

first we solve right side of the equation.



Add 23 both side of the equation.




or

Therefore, the value of
or 
Remember PEMDAS
first add -3p^2 and 7p^2 to get 4p^2.
next add 8p^2 and 4p^2 to get 12p^2
12p^2 is your answer