Answer:
The correct answer is False.
Explanation:
Mediation is an alternative method of resolving conflicts, which has the intrinsic purpose of reaching the integral solution of a conflict between parties (they can be two or more people), thus avoiding reaching the judicial instance. The guiding principles that guide and implement mediation are: confidentiality, voluntariness, orality between the parties and full communication between them, the impartiality of the intervening mediator and the neutrality of the mediator regarding the matter brought into question.
It is based on democracy, social pacification, individual and social dialogue, respect, and consensus for coexistence. It consists of the intervention of a third party in a conflict, the mediator, in order to facilitate the rapprochement of the opposing parties and promote a negotiation process that allows reaching an agreement agreed and accepted by the parties that ends the conflict.
Cost Principle,
<span>requires that assets be recorded at the cash amount (or its equivalent) at the time that an asset is acquired.</span>
Answer:
The yield to call is 2.24%.
Explanation:
To calculate the yield to call, you can use the following formula:
YTC = (C + (CP - P) / t) / ((CP + P) / 2)
YTC= Yield to call
C= Annual Coupon: 0
CP= Call price of the bond: $509
P= Price of the bond: $455
t= time remaining until call date: 5
YTC= (0+(509-455)/5)/((509+455)/2)
YTC=(54/5)/(964/2)
YTC= 10.8/482
YTC= 0.0224= 2.24%
<u>Answer:</u> Option C
<u>Explanation:</u>
The total compensation along with benefits are $72000. When the employee benefits calculated the annual gross pay given in option C . 12.5% interest calculated on $64000 will give total compensation of $72000.
Calculation of total compensation
Employee benefits = $64000 x 12.5/100
=$8000
Annual compensation= $64000 +$8000
=$72000
Answer: (D) Accept the risk
Explanation:
According to the given question, the one of the best solution is to accept the risk as the 2 given risks in the project cannot be removed or also outsourced from the given project scope.
Accepting the risk is one of the risk retention process in which we sometimes cannot avoid the given risk in the risk management and it is commonly found in the various types of investment process and also in the business.
On the basis of the given scenario, we could not eliminate the two risks in the project so the best solution is to using the risk acknowledgement due to some limitations. Therefore, Option (D) is correct answer.