Answer:
a. intrinsic rewards
Explanation:
Intrinsic rewards at the workplace are those that meet personal, internal needs. These intrisic rewards can be summed up in job satisfaction and sense of accomplishment, but what makes a job satisfying, and what makes a worker feel accomplished is subjective, and varies from person to person.
Mike is focusing on the intrinsic rewards of his new job because he is giving more importance to this subjective aspects explained above than to external factors such as status, or wage.
it would be a as a team I hope this helps
<span>A situation in which quantity demanded is greater than quantity supplied best describes shortage. Shortage is when any product or service lacks the means to provide or satisfy its demand. A shortage in the product or service usually results to a price increase. On the other hand, a surplus results to a price decrease.</span>
Answer:
A
Explanation:
Net present value is the present value of after-tax cash flows from an investment less the amount invested.
Only projects with a positive NPV should be accepted. A project with a negative NPV should not be chosen because it isn't profitable.
When choosing between positive NPV projects, choose the project with the highest NPV first because it is the most profitable.
NPV can be calculated using a financial calculator
Cash flow in year 0 = $-165,000
Cash flow in year 1 - 6 = $45,000
I = 12%
NPV = $20,013.33
the project should be approved because NPV is positive
To find the NPV using a financial calculator:
1. Input the cash flow values by pressing the CF button. After inputting the value, press enter and the arrow facing a downward direction.
2. after inputting all the cash flows, press the NPV button, input the value for I, press enter and the arrow facing a downward direction.
3. Press compute