Answer:
$240.76
Explanation:
The formula to determine the annual deposit is :
p = FV / annuity factor
Annuity factor = {[(1+r)^n] - 1} / r
FV = Future value
P = Present value
R = interest rate
N = number of years
Annuity factor = (1.07^11 - 1) / 0.07 = 15.783599
p = $3800 / 15.783599 = $240.76
Answer:
a. Equity alliance
Explanation:
Equity alliance -
It is the process , in which one of the company take the equity stake of the other company and vice versa , is referred to as equity alliance .
Due to this , the company becomes shareholder and stakeholder of each other .
The share acquired is the minor one , so that the company still have the power of decision making .
Hence , same case is shown in the question ,where the Moon Star Products Inc.buys the 40 % of the stock of Gold Logistics .
In forward and futures contracts, the risk of non-fulfillment of contract terms is most likely borne by <u>both parties</u><u> to the contract</u>.
<h3>What are forward and futures contracts?</h3>
The difference between a forward and futures contract lies in their establishment.
A forward contract is a personal arrangement traded over the counter whereas, a futures contract is a standardized contract made through an established exchange.
Thus, in forward and futures contracts, the risk of non-fulfillment of contract terms is most likely borne by <u>both parties</u><u> to the contract</u>.
Learn more about forward and futures contacts at brainly.com/question/15581105
#SPJ12
Answer:
c) finish-to-start; start-to-start
Explanation:
Project dependencies are the time relationships between a predecessor and a successor in project management. In other words, these dependencies describe which activity among the two needs to start earlier or later and when it needs to start or finish compared to the other one.
The most common type of dependency in all projects (no matter the nature or industry) is the finish-to-start one, where the activity A needs to be completed before activity B starts, e.g. base nail polish has to be put before the top coat gets put on the nails.
The second most common type of dependency is the<em> start-to-star</em>t one, where two activities need to start at the same time. This is common for activities where synchronization is paramount.