Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.
Answer:
1. 7.2
2. 9
Explanation:
take 72 and divide by number of years
72/x= ROI
Answer:
The answer is: D
Explanation:
Program trading is the use of computer programs or algorithms to trade a portfolio of stocks at a high frequency and in large numbers. These algorithms, essentially 'machine traders', are created to make trades on behalf of humans and are anticipated to have more precision and speed than human traders. However, these trades are created, monitored and analysed by human traders. The New York Stock Exchange classifies the coordinated trading of a group of 15 or more stocks with a combined market value of $1, 000, 000 as program trading.
Answer:
NAV=$63.114615
The NAV of the fund=$63.114615
Explanation:
Stock Shares stock Price
A 13,500 $83
B 33,000 $16
C 20,000 $59
D 71,000 $21
Total Assets= ( 13,500*$83)+( 33,000*$16)+( 20,000*$59)+(71,000*$21)
Total Assets= $4,319,500
Formula for NAv:
NAV=
NAV=
NAV=$63.114615
The NAV of the fund=$63.114615