<em><u>Answer</u></em>
5 hours
<em><u>Explanation</u></em>
The two working together can finish a job in

Also, working alone, one machine would take one hour longer than the other to complete the same job.
Let the slower machine working alone take x hours. Then the faster machine takes x-1 hours to complete the same task working alone.
Their combined rate in terms of x is

This should be equal to 20/9 hours.

Multiply through by;





Factor to get:


It is not feasible for the slower machine to complete the work alone in 4/9 hours if the two will finish in 20/9 hours.
Therefore the slower finish in 5 hours.
Answer:
1. You can invoke or call a method from another program or method: TRUE
2. When methods must share data, you can pass the data into and return the data out of methods: TRUE
3. A method could be called using any numeric value as an argument, whether it is a variable, a named constant, or a literal constant: TRUE
Explanation:
Answer: Please find below the answer along with explanation.
Explanation:
For a given communication channel (for instance, a LAN segment using Ethernet ) the Bandwidth refers to the theoretical maximum data rate that the channel can support, for instance, 100 Mbps in a 100Base T network.
The throughput, instead, refers to the actual data rate achieved in a given communications channel, taking into account the different channel impairments.
For instance, in a LAN segment that uses the original Ethernet 802.3 standard (CSMA/CD), a frequent occurrence of collisions can take down the actual data rate from the theoretical 100 Mbps to a very lower figure, i.e., 5 Mbps.
Answer:
B
Explanation:
the software needs to share thus should be networked
Explanation:
the perimeter of an aluminium sheet is 120 CM if its length is reduced by 10% and its breadth is increased by 20% the perimeter does not change find the measure of the length and the breadth of the sheet