Answer: b)because near-critical paths could become critical paths with small delays in these activities
Explanation: Program evaluation and review technique(PERT) technique is used for management of the project .The organizing, maintenance,coordination of any task is done by this chart. The non-critical activities need to be observed carefully because they may create near-critical methods which can lead to complexity.
Other options are incorrect because not all activities are equally rather monitoring is done to avoid errors and slack can occur at any path . Small delays can be caused but not complete project can get delayed and there can be risk of complexity rather than being uncompleted.Thus, the correct option is option(b).
Answer:
suppose i was i would tell them i dont know and walk away
Explanation:
in thoery this is correct
you said suppose so i answerd
there is no use in reporting or getting this taken down
nether is it right
im not stealing points
Because in thoery its an answer
<em><u>THIS IS MY PROTEST</u></em>
According to Newton's third law, for every action force there is an equal (in size) and opposite (in direction) reaction force.