In the following Earliest Start Time (EST) graph, assume each unit of time is an hour.
1 answer:
8
Step-by-step explanation:
- Critical Path Analysis is presented using the circle and arrow diagrams.
- Earliest Start Time = the earliest possible time of starting the activity
- An arrow running between two event circles shows the activity needed to complete that task.
- All arrows run left to right
- Time for doing just task E = 8 hours (as shown in the figure)