Hexagon has six edges. The figure you're trying to figure out is hexagon I guess.
25 million
number of bacteria doubles every minute
Okay so first, area is length times width, so 1/4x*x would be first = 1/4(x^2)=64. Then area or x = 16 or -16
perimeter would be width times two plus length times two. I recommend using math papa to calculate these numbers.
Answer:
f(2) = -40
Step-by-step explanation:
Just substitute x=2 into the function:
f(x) = 2x³ - 3x² - 18x - 8
f(2) = 2(2)³ - 3(2)² - 18(2) - 8
f(2) = 2(8) - 3(4) - 36 - 8
f(2) = 16 - 12 - 44
f(2) = 4 - 44
f(2) = -40
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.