Answer:
b. The project's schedule will slip only if the float / slack period for the critical path activities is not enough to resolve the resource overload issue.
Explanation:
This is true because, the resource overload will be an impediment to the critical activities going on in the project. There supposed to be an equilibrium between the resource and the project schedule in-order to ensure completion of the project within the given time frame.
Answer:
The answer is b
Explanation:
both imports and exports do A and D and they can both specialize in different areas but their extent of what they sell/get is different
Your answer is A) Facilitation Payments.
Hope this helps! =)
Answer:
The answer is: The COGS is $635
Explanation:
We will use the following entries:
- Initial merchandise inventory $210
- Purchased merchandise inventory $635
- Ending merchandise inventory $160
Cost of goods sold = initial inventory + purchases - ending inventory
Cost of goods sold = $210 + $635 - $160 = $685
Answer:
money supply = 32 million
Explanation:
The reserve requirement is the money banks keep in their vaults against the deposited money.
The supply of money is affected by reserves and the supply of money can be increased if we lower the reserve requirements.
The money supply is calculated as
money supply = deposits*money multiplier
Where money multiplier is ( 1/ % of reserve requirement)
money supply = deposits*( 1 / % of reserve requirement)
money supply = 1600000*( 1/0.05)
money supply = 32000000
money supply = 32 million