Answer:
Option (B) is correct.
Explanation:
Equivalent units of production(EUP) - Materials:
= Transferred out + Ending balance
= 10,451 units × 100% + 3,483 units × 100%
= 10,451 + 3,483
= 13,934
Equivalent units of production(EUP) - conversion:
= Transferred out + Ending balance
= 10,451 units × 100% + 3,483 units × 36%
= 10,451 + 1,253.88
= 11,704.88
Material cost = 
Material cost = 
= 73,157
Conversion cost = 
Conversion cost = 
Conversion cost = 
= 53,715
Therefore,
Total cost of units completed during the period(10,451 units):
= Material cost + Conversion cost
= 73,157 + 53,715
= 126,872
Answer:
2. in the short run, as aggregate demand increases, unemployment is reduced.
Explanation:
The government misjudging the natural rate of unemployment to be much lower than it actually is, and thus undertaking expansionary fiscal and monetary policies to try to achieve the lower rate. These policies might at first succeed because in the short run, as aggregate demand increases, unemployment is reduced due to the expansionary policies.
Answer:
$481,000
Explanation:
Bond issue costs are either direct or indirect costs:
- direct costs include underwriting fees, listing fees, professional fees, compliance costs and other costs related to the IPO or APO (secondary issues), e.g printing costs
- indirect costs include underpricing costs (IPO pricing is too low) and loss of proprietary information
Total bond issue costs = $22,000 + $170,000 + $9,000 + $280,000 = $481,000
Financial venture. even his wife was supportive. albert liked a number of riskier company
Answer:
Units transferred out = 760
Explanation:
If we assume that all units are completed in the order of arrival i.e (FIFO), then the units transferred out is the sum of the opening inventory and the units started and completed in the period. The units started and completed in the period is referred to fully-worked.
Fully worked is computed as the units started in the period less the closing inventory .
Fully- worked = 800 - 240 = 560
The units transferred out = opening inventory + Fully-worked
= 200 + 560 = 760
Units transferred out = 760
Note we assumed that the units of the inventory( started last period i.e January) would be worked on first in the month of February before any other units. So, it is assumed completed by the end of February