Stanley Plog was the researcher who identified 3 types of travelers
Answer:
The correct answer is A that is late start date.
Explanation:
Late start date is the filed which comprise of the latest date on which a task could be started without delaying the finish of the project.
The date is grounded on the date when the task is started and also on the late start of the task, late finish dates of the tasks predecessor and the successor as well and also on other constraints.
So, the late start date for the activity is the latest possible time.
Answer:
Options B and C are correct.
- Marginal profit is negative.
- Profit is positive.
Explanation:
At q = 150
R = 80q = 80(150) = 12,000
C = 0.002(150)3 + 22(150) + 750 = 6750 + 3300 + 750 = 10,800
R > C so first is incorrect.
MR = 80
MC = 0.006(150 x 150) + 22 = 135 + 22 = 157
MC > MR so B is correct.
Profit = TR - TC = 80(150) - 0.002(150)3 - 22(150) - 750 = 12000 - 10800 = 1200
Profit is positive.
Marginal profit = MR - MC = 80 - 157 = - 77
MR is Negative
Please forgive me if I’m wrong
I think it would be a.true
Answer:
a. Shorten his portfolio duration
Explanation:
The best action to take in order to capitalize on expectations of increasing interest rates would be to shorten his portfolio duration. This is because an increase in the interest rate causes his portfolio value to decrease, yet if the duration of his portfolio is shortened then the change/decrease in value will be lesser than if done otherwise.