Answer: statistician automotive engineer customer service specialist data modeler broadcast technician video systems technician
Explanation:
Answer:
See the program code below.
Explanation:
def cube_SA(edge):
edge = int(input("Enter the cube's edge: "))
sa = edge * edge * 6
print("The surface area is {} square units".format(sa))
cube_SA(4)
Best Regards!
Navigation items are used for moving from one part of the part to a destination using actions and also for passing information. The right option is <em>C. In the navigation menu and the first four items of the </em><em>navigation bar</em><em>, when users are in the app </em>
<em />
There are different methods/ways to implement the Navigation component in a mobile application, we have the following type of Navigation Implementation
- Bottom Navigation
- Drawer Navigation(Slides from Left to right)
- Top Navigation
Learn more about Navigation here:
brainly.com/question/8908486
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.