Answer:
6.666666666666... minutes per mile
So, if we look at the number pattern, we can see the numbers go up by 4.
The rule is Add 4.
So, to find the next two terms, we would add 4 to the last number shown, which is 15.
15 + 4 = 19
19 + 4 = 23
So, the next two terms are →19← and →23←.
Glad I could help, and good luck!
AnonymousGiantsFan
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Group and factor
group y's with y's and z's with z's
(y²-10y)+(10z-yz)
factor
y(y-10)+z(10-y)
force undistribute -1
-y(10-y)+z(10-y)
factor
(10-y)(-y+z)
(z-y)(10-y) or
(y-z)(y-10)