Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.
If you’re cutting it into half inch pieces, you’ll take the length of the roll and multiply it by 2, so 13•2=26
1: always rearrange the equation to y = mx + c so....
x - y = o
x = y
So the gradient is 1 and it intersects the y axis at (0,0)
The three points could be (1,1), (2,2), (3,3) and so on
2: -x -2y = -10
Multiply everything by -1
x + 2y = 10
2y = 10 - x
y = 5 - x/2
The y intercept is 5 so you could use the point (0,5), (2,4), (4,3) and so on
3: x + y = -2
y = -2 - x
The y intercept is -2 so you could use the points (0,-2), (2,-4), (3,-5) and so on
4: -3y =-x -7
Multiply everything by -1
3y = x + 7
y = x/3 + 7/3
The y intercept is 7/3 so you could use the points (0,7/3), (3,10/3), (6,13/3) and so o
5: -y = -x + 1
y = x - 1
The y intercept is -1 so you could use the points (0,-1), (2,1), (3,2) and so on
Hope this helps! Any questions let me know :)