Answer:
$30,000 under applied
Explanation:
For computing the over applied or under applied, first, we have to compute the predetermined overhead rate. The formula is shown below:
Predetermined overhead rate = (Total estimated manufacturing overhead) ÷ (estimated machine hours)
= $1,200,000 ÷ 300,000 hours
= $4
Now we have to find the applied overhead which equal to
= Actual machine hours × predetermined overhead rate
= 280,000 × $4
= $1,120,000
So, the ending overhead equals to
= Actual manufacturing overhead - applied overhead
= $1,150,000 - $1,120,000
= $30,000 under applied
Answer: a motion for summary disposition or summary judgement.
Explanation:
A summary judgement is also known as summary disposition or judgement as a matter of law. A summary judgement is a judgement that is entered by a court for a party at the expense of another party which is summarized. It is a judgement without a full trial.
Summary judgement can be as a result of discretion in the case or merits of a case. The above case is an example as both parties agree to the facts with Delta supporting it with sworn statements.
Answer:
d. an offer and an acceptance.
Explanation:
A contract exists where each involved party agrees to fulfill its obligations as per the terms of the agreement. The two or more parties involved are in consensus regarding the subject matter. A contract valid and in force, once the offeror makes the offer, and the offeree accepts it.
Steel and mike are in are contract. Mike has accepted the offer by steel. Other elements that must be present for a contract to be valid are the existence of consideration, mutual obligations, and the ability to fulfill one's responsibility.
Answer:
Option (A) is correct.
Explanation:
Given that,
Mean daily demand, M = 20 calculators per day
Standard deviation, SD = 4 calculators per day
Lead time for this calculator, L = 9 days
z-critical value (for 95% in-stock probability) = 1.65 (From z tables)
Normal consumption during lead-time:
= Mean daily demand × Lead time
= 20 × 9
= 180 units of calculator
Safety Stock = z value × SD × L^(0.5)
= 1.65 × 4 × (9)^(0.5)
= 1.65 × 4 × 3
= 19.8 units
Reorder Point = Normal consumption during lead-time + Safety Stock
= 180 units + 19.8 units
= 199.8 or 200 units (Approx)
Answer:
Option b is correct
Explanation:
The requirement of this service is to be independently derived because the procedures vary according to needs of the parties involved in the agreement.