Answer:
Explanation:
Base on the scenario been described in the question,Hey, since there are multiple sub-parts posted, we will answer first three sub-parts. If you want any specific sub-part to be answered then please submit that sub-part only or specify the question number in your message.
2
Compute the net present value to make decision for buying the new Backhoes or keeping the old:
We can fine the calculations in the file attached below
The Layout would be the answer to this question
Answer:
The price of the bond is $1000. Thus, option a is the correct answer.
Explanation:
The price of a bond is calculated using the present value of the interest payments made by the bond, which is in the form of an annuity, plus the present value of the face value of the bond. The present value is calculated by discounting the annuity of interest and the face value by the YTM or yield to maturity. In case YTM is not provided, we assume that it is same as or equal to the coupon rate paid by the bond.
The formula for the price of the bond is attached.
Bond Price = 25 * [(1 - (1+0.025)^-8) / 0.025] + 1000 / (1+0.025)^8
Bond Price = $1000
Answer:
The correct answer is True.
Explanation:
The steps to follow to create a work breakdown structure are as follows:
1. Organize a meeting and share with the main stakeholders: team members are one of the most valuable assets in the process of creating the work breakdown structure. They have the knowledge, experience and creativity necessary to define each deliverable reaching the most specific details.
2. Complete the definition of all project deliverables: it is about going one step beyond the level reached in the planning and 100% complete the information on all project deliverables, including internal and external, associating each one with its estimated completion time.
3. Break down each deliverable into smaller, more manageable parts: it is about achieving a realistic level of work planning by the project manager, which ensures that, without interfering with the total estimated project deadline and the overall plan, it can be completed by the work teams. It is about determining work packages. These units constitute the lowest level of the EDT and are pieces of work that are specifically assigned to a person or a team of people to be completed, under the supervision of the Project Director. It is recommended that they focus on a single point of responsibility. The work packages will be used later to define the activities and tasks in which the project is divided.
4. Review the results obtained: with the stakeholders, both at the time of finalizing the elaboration of the work breakdown structure, and when modifications or updates are included, if applicable. It is essential to avoid overlaps.