Answer:
Minimum cycle time = time for longest task = 2.4 minutes
Maximum cycle time = sum of the times to complete all the tasks = 18 minutes
Step-by-step explanation:
For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.
For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.
Answer:
1.17*10²
Step-by-step explanation:
Diameter of the sun is about 1.4 × 10⁶ km
1.4*10⁶ km = 1,400,000
Diameter of the planet venus is about 12000 km
12000 km = 1.2 × 10⁴
Ratio of the diameters
Sun : Venus
1.4 × 10⁶ km : 1.2 × 10⁴
1.4 × 10⁶ km / 1.2 × 10⁴
1.4 / 1.2 × 10^6-4
1.166 × 10²
Approximately
1.17 × 10²
Answer:
There is no question so I can not respond with a answer.
Step-by-step explanation:
Answer:
See explanation below
Step-by-step explanation:
The best explanation is noticing that in order to get from the point R (12, 1) to the point Q (7, 4) we move 5 units to the left and 3 units up. And to go from point Q (7, 4) to point P (2, 7) we do exactly the same: move 5 units to the left and 3 units up. That means that these points are all connected via the same rate of change: - 3/5, which is in fact the slope of the line the three points belong to.
Answer:
1,980 would be the area and the perimeter would be 39 im pretty sure