A decline in the real GDP that occurs for at least two or more quarters is called a depression. The correct option among all the options that are given in the question is option "b". There is a very thin line of difference between recession and depression. when the real GDP falls for a repeated number of periods, then it is depression.
Answer:
Explanation:
X - number of units sold
Total cost for production = 1,500,000 + 1600X
Total cost for purchasing = 2000X
a. For 4000 units sold
Total cost for production = 1,500,000 + 1600 * 4000 = $7,900,000
Total cost for purchasing = 2000* 4000 = $8,000,000
In this case producing is cheaper. Therefore, it is better to produce
b. Y - break-even point
Then : 1,500,000 + 1600 * Y = 2000* Y
So 1,500,000 = 400 Y
Y = 3750
At №of units less than 3750 purchasing will be the better option
And above 3750 producing will be the better option
The entry is record in book as
Date Particular L.F. Dr. Amt. Cr. Amt.
Income summary a/c $460,500
To Mo a/c $69,300
To Lu a/c $269,500
To Barb a/c $431,200
What is net income?
The total amount of firm profit after deducting all taxes, costs, and interest is referred to as "net income."
Particulars Mo Lu Barb
Capital invested $69,300 $269,500 $431,200
Profit sharing ratio 20/100 40/100 40/100
Profit ($460,500) 92100 184200 184200
As a result, Mo is 92100; Lu is 184200; Barb is 184200 as profit.
Learn more about on net income, here:
brainly.com/question/15570931
#SPJ 1
Answer:
The correct answer is True.
Explanation:
The steps to follow to create a work breakdown structure are as follows:
1. Organize a meeting and share with the main stakeholders: team members are one of the most valuable assets in the process of creating the work breakdown structure. They have the knowledge, experience and creativity necessary to define each deliverable reaching the most specific details.
2. Complete the definition of all project deliverables: it is about going one step beyond the level reached in the planning and 100% complete the information on all project deliverables, including internal and external, associating each one with its estimated completion time.
3. Break down each deliverable into smaller, more manageable parts: it is about achieving a realistic level of work planning by the project manager, which ensures that, without interfering with the total estimated project deadline and the overall plan, it can be completed by the work teams. It is about determining work packages. These units constitute the lowest level of the EDT and are pieces of work that are specifically assigned to a person or a team of people to be completed, under the supervision of the Project Director. It is recommended that they focus on a single point of responsibility. The work packages will be used later to define the activities and tasks in which the project is divided.
4. Review the results obtained: with the stakeholders, both at the time of finalizing the elaboration of the work breakdown structure, and when modifications or updates are included, if applicable. It is essential to avoid overlaps.