1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Andrews [41]
4 years ago
13

Please help i will give brainliest.

Mathematics
1 answer:
LenKa [72]4 years ago
6 0
2x+5=5x-25
Subtract 2x from both sides
Add 25 to both sides
30=3x
Then replace x with 10
2(10)+5 =25
25 times 2 =50
You might be interested in
Which of the following describes a rate?
Westkost [7]

Answer:

2. Anisa gets paid $12 per hour describes a rate.

Step-by-step explanation:

A rate is something that says (something) per (something.) For example, the cheetah ran 240 miles <em>per</em> minute is considered a rate.

Rates usually <em>end</em> with one, since they say that (something) every 1 (minute, hour, etc.) whether it's a place or thing.

Hope this helps! :)

8 0
3 years ago
A tree casts a shadow 21 ft long while Enzo who is 5 ft tall casts a shadow 6 ft long
adelina 88 [10]
Are you asking for the height of the tree? If so, the answer is 17.5 ft.
Be more precise next time, and I hope this helps.
5 0
4 years ago
Half of a sphere is stacked on top of a cone. They both share a circular base. The radius of the circle is 6 millimeters. The he
kherson [118]

Answer:

312π mm3

Step-by-step explanation: yes

5 0
3 years ago
Read 2 more answers
M5_A3. The expected project completion time for the construction of a pressure vessel is 18 monthsand the project variance is 7.
snow_tiger [21]

Answer:

a) 0.3520

b) 0.9884

c) 0.1292

d) 0.1292

e) 0.7648

Step-by-step explanation:

Problems of normally distributed samples can be solved using the z-score formula.

In a set with mean \mu and standard deviation \sigma, the zscore of a measure X is given by

Z = \frac{X - \mu}{\sigma}

After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X.

In this problem, we have that:

The expected project completion time for the construction of a pressure vessel is 18 months. So \mu = 18.

And the project variance is 7. The standard deviation is the square root of the variance, so \sigma = \sqrt{7}.

a) What is the probability that the project will require at least 19 months?

The pvalue of the zscore of X = 19 is the probability that the project will require less than 19 months. So the probability that the project will require at least 19 months is the subtraction of 1 by this pvalue.

Z = \frac{X - \mu}{\sigma}

Z = \frac{19 - 18}{\sqrt{7}}

Z = 0.38

The pvalue of Z = 0.38 is 0.6480.

So the probability that the project will require at least 19 months is 1 - 0.6480 = 0.3520.

b) What is the probability that the project will be completed within 24 months?

This is the pvalue of the zscore of X = 24.

Z = \frac{X - \mu}{\sigma}

Z = \frac{24 - 18}{\sqrt{7}}

Z = 2.27

The pvalue of Z = 2.27 is .9884. This means that the probability that the project will be completed within 24 months is .9884.

c) What is the probability that the project will require at least 21 months?

Same logic as a). We find the pvalue of the zscore of X = 21, then we subtract 1 by this value.

Z = \frac{X - \mu}{\sigma}

Z = \frac{21 - 18}{\sqrt{7}}

Z = 1.13

The pvalue of Z = 1.13 is 0.8708.

So the probability that the project will require at least 21 months is 1 - 0.8708 = 0.1292.

d) What is the probability that the project will be completed within 15 months?

Same logic as b). This is the pvalue of the zscore of X = 15.

Z = \frac{X - \mu}{\sigma}

Z = \frac{15 - 18}{\sqrt{7}}

Z = -1.13

The pvalue of Z = -1.13 is .1292. This means that the probability that the project will be completed within 15 months is .1292.

e) What is the probability that the project will take between 16 and 24 months to complete?

This is the pvalue of Z = 24 subtract by the pvalue of Z = 16.

In b), we found that the pvalue of Z = 24 is .9884

Now we find the pvalue of Z = 16

Z = \frac{X - \mu}{\sigma}

Z = \frac{16 - 18}{\sqrt{7}}

Z = -0.76

The pvalue of Z = -0.76 is 0.2236

So the probability that the project will take between 16 and 24 months to complete is 0.9884 - 0.2236 = 0.7648

8 0
4 years ago
Can I get some help on this I have so many assignments to do and I just want to go to sleep
AfilCa [17]
Hi! It’s me from your other post! Here’s my work for you! It’s been awhile since I’ve done this stuff so I’m really sorry if I get you a bad grade! I just wanted to help out:))

7 0
3 years ago
Other questions:
  • Which statement is true?
    15·1 answer
  • 174 ÷ 6 Show work help
    6·2 answers
  • To divide using a model, 3/8 / 1/4 which of the following are true? Select all that are correct.
    10·1 answer
  • Is A correct ? please help
    7·1 answer
  • Can someone help me please
    14·1 answer
  • julia earns $5 each day running errands for a neighbor. How much will julia earnif she runs errands for 6 days in one month?
    15·2 answers
  • Why are some right triangles considered special?
    11·1 answer
  • 2x^2-7x-4=0<br> x=?; x=?
    6·2 answers
  • The ratio of boys to girls is 5:6 if there are 72 girls what is the total number of students in the year level?
    13·2 answers
  • What is the percent of decrease from 600,000 to 60,000? Write your answer using a percent sign (%).​
    9·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!