Answer:
A. Project management
Explanation:
It helps by identifying the plans and estimating the minimal possible time and cost needed to complete a project or development
Answer:
Option A,$4,200 is the correct option to the question
Explanation:
The fixed manufacturing overhead budget for the month is the difference between budgeted fixed manufacturing overhead cost and actual fixed manufacturing overhead cost for the month as shown by the computation below:
Fixed manufacturing overhead budget variance =$52,000-$56,200=-$4,200
The variance is an unfavorable since the actual overhead cost of $56,200 outweighs the budgeted cost of $52,000,hence the correct option is A
Answer:
Explanation:
The computation of the depreciation per units or bolts under the units-of-production method is shown below:
= (Original cost - residual value) ÷ (estimated miles)
= ($35,000 - $5,000) ÷ (100,000 miles)
= ($30,000) ÷ (100,000 miles)
= $0.3 per mile
For the first year, it would be
= Miles in first year × depreciation per mile
= 20,000 miles × $0.3
= $6,000
And, For the third year, it would be
= Miles in third year × depreciation per mile
= 24,000 miles × $0.3
= $7,200