<span>(a) y - 0 = -3/5(x - 3) . . . . . . the 1st selection
(b) </span><span>y = -3/5x + 9/5 . . . . . . . . the 3rd selection</span>
Answer:

Step-by-step explanation:
We want to simplify:

We rewrite as positive index to get:

This simplifies to

This will finally give us:

We cannot simplify further.
Hence the simplest form is 
Answer:D) A positive correlation between the height of a woman and the height of her brother
B) a negative correlation between the length of digital photos uploaded to a website and the amount of storage space that is left
Step-by-step explanation:
Answer:
Jim's path is the critical path on this activity graph.
Step-by-step explanation:
Critical Path:
Critical path is the the longest path in the project task paths. It shows the least amount of time in which project can be completed. It can be find by looking at the longest path in the network diagram of the project; not in term of nodes or activities instead in term of days.
In given case:
Path 1 Bill task's total duration= 6 days
Path 2 Jim's task's total duration= 17 days
Path 3 Betty task's total duration= 7 days
Path 4 Cynthia task's total duration= 14 days
Hence the longest path i.e. critical path is of Jim's activity path !