Answer:
sorry i don't know
Step-by-step explanation:
Answer:
The area is 432cm squared.
Step-by-step explanation:
To find the area, first you split the figure into 2 rectangles.
The rectangle facing up would be 8cm by 30cm, and the rectangle pointing to the left would be 8cm by 24cm (because you subtract 8 by 32). Next, with those numbers, you can easily find the area. 8cm x 30cm equals to 240cm squared, and 8cm x 24cm equals to 192cm squared. Lastly, you add the both of the areas together, 240cm and 192cm, and you get 432cm squared.
Answer:
first one: <u>3</u>
second one: <u>b</u>
third one: <u>3.2</u>
Step-by-step explanation:
first one:
21 x ________ ÷ 3 = 21
rewrite equation:
21 ÷ 3 x ___ = 21
7 x ___ = 21
(21 / 7 = 3)
7 x 3 = 21
second one:
b x h ÷ h = ___
B
third one:
876 x 3.2 ÷ ______ = 876
2803.2 ÷ ___ = 876
(2803.2 / 876 = 3.2)
2803.2 x 3.2 = 876
Answer: 8 minimum work stations is what would be needed.
Step-by-step explanation:
The cycle time is computed as the operating time daily divided by the scheduled output.
It is important to note that the daily capacity of the operation layout is the operating time divided by the cycle time.
Therefore,
If you need to produce 30units/hour.
The average cycle time is as follow:
The average cycle time is the average time between the completions of units.
60/30= 2 average cycle time
=16/2
=8
8 work stations is the minimum number that would be needed.
It is important to know that in an assembly line balancing, the minimum number of work station is the ratio of the sum of all tasks time to the cycle time.