Answer:
The answer would be X=2 .
Step-by-step explanation:
Hope it helps u :)
Answer:
42
Step-by-step explanation:
73*11= 803
845-803= 42
The expected completion time is μ = 40 weeks.
The random variable, X = 38 weeks (the probable time)
If the standard deviation is σ, then the z-score is z = (x - μ)/σ.
Let us test the given standard deviations.
When σ=1,
z = (38-40)/1 = -2
From standard tables,
P(x<=38) = P(z<=-2) = 0.0228 =2.3%
When σ=2,
z = (38*40)/2 = -1
P(x<=38) = P(z<=-1) = 0.1587 = 15.9%
When σ=4,
z = (38-40)/4 = -0.5
P(x<=38) = P(z<=-0.5) = 0.3085 = 30.9%
Answers:
z=1 => 2.3%
z=2 => 16% (approx)
z=4 => 31% (approx)
Step-by-step explanation:
3a²-7a−6
Factor the expression by grouping. First, the expression needs to be rewritten as 3a
2
+pa+qa−6. To find p and q, set up a system to be solved.
p+q=−7
pq=3(−6)=−18
Since pq is negative, p and q have the opposite signs. Since p+q is negative, the negative number has greater absolute value than the positive. List all such integer pairs that give product −18.
1,−18
2,−9
3,−6
Calculate the sum for each pair.
1−18=−17
2−9=−7
3−6=−3
The solution is the pair that gives sum −7.
p=−9
q=2
Rewrite 3a
2−7a−6 as (3a
2−9a)+(2a−6).
(3a 2−9a)+(2a−6)
Factor out 3a in the first and 2 in the second group.
3a(a−3)+2(a−3)
Factor out common term a−3 by using distributive property.
(a−3)(3a+2)
Answer:
0.75ft per square
Step-by-step explanation:
We know that the number of squares is 24 so we need to determine the dimension of 1 square.
We know the width is 4.5 and we also know that there are 6 squares within that area.
Therefore we can use a fraction to find our answer.