The available options are the following:
-Board members serve on multiple boards
-People with knowledge of the firm's history are replaced with those who may not know as much information
-Less frequent board meetings
-Better decisions about important issues
Answer:
-People with knowledge of the firm's history are replaced with those who may not know as much information
Explanation:
Considering the available options, the option that appears negative and related to the point being discussed is
"People with knowledge of the firm's history are replaced with those who may not know as much information."
It is straightforward, as changing the board of directors will at some point lead to a time where the new member in the board of directors will just be a competent worker but has no history with the company.
Answer:
The answer is (D) all of the above.
Explanation:
Managing diversity is a workplace practice where companies focus their efforts in establishing a working environment where people with various demographic characteristics can thrive and perform to their fullest potential according to their work responsibilities. This means employers, more specifically, the human resources department, need to pay attention to the individuals’ background in order to create a work environment that is fair to each individual.
Answer:
a) true
Explanation:
Support Function include Information Technology, Human Resources, Finance and Marketing. These are there to ensure that conversion process is efficient by providing support services such as sourcing of talent, fund management, communication.
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186
Answer:
The correct answer to the following question will be "$831".
Explanation:
- Mary Matthews is a married woman, however, her gross salary is $950 per two weeks, as well as the compensation amount, is 2. The year 2018 married bi-weekly wage category table would be used to determine the sum to be withheld underneath the framework of wage class.
- The applicable limit for $950 throughout the list is between $945 or $965 as well as $19 seems to be the amount of funding tax must keep for 2 allowances.
So that the compensation would be:
The sum is taken by her to their residence = Gross Salary - Income Tax deferred - Contribution towards 401k
= $950 - $19 - $100
= $831