An invoice is a document given from the seller to the buyer stating the quantity of products bought, agreed prices and transactions made between the two parties. If the buyer bought the product in June 10 and decides to pay on the 19th, only 9 days have passed since the date of purchase. This is inclusive of the agreement written that 2% discount is given if paid not more than 10 days. Therefore, the check should be
($5,000)(1-.0.02) = $4900
Answer:
the fund balance is $1,727,056.25
Explanation:
The computation of the fund balance is shown below:
Given that
PMT = $125,000
NPER = 10
RATE = 7%
PV = $0
The formula is shown below:
= -FV(RATE,NPER,PMT,PV,TYPE)
After applying the above formula, the fund balance is $1,727,056.25
Here basically the future value formula should be applied
Answer:
Bait and Switch
Explanation:
Bait and switch is a deceptive sales technique that draws customers in with the promise of low prices and then "switches" to say that the promised item is not available. It is actually illegal under <em>some </em>circumstances in the United States.
Answer:
Year Cash Flow (A) Cash Flow (B)
0 -37,500 -37,500
1 17,300 5,700
2 16,200 12,900
3 13,800 16,300
4 7,600 27,500
1) Using an excel spreadsheet and the IRR function:
IRR project A = 20%
IRR project B = 19%
2) Using the IRR decision rule, Bruin should choose project A.
3) In this case, since the length of the projects is only 4 years, then there should be no problem with the IRR decision rule, but for projects with longer time lengths, the discounts rates might vary and the best option is to use the modified internal rate of return (MIRR). But in this case the NPV of project B is higher, then Bruin should probably project B because it has a higher NPV. The NPV is always more important then the IRR.
4) Again using an excel spreadsheet and the NPV function:
NPV project A = $6,331
NPV project B = $8,139
5) first we must subtract cash flows from A by the cash flows from B:
1 $11,600
2 $3,300
3 -$2,500
4 -$19,900
then we calculate the IRR = 16%
Bruin should be indifferent between the two projects at a 16% discount rate. That means that at discount rates above 16%, you should choose project A, but at discount rates below 16%, you should choose project B