Answer:
D
Explanation:
option D is correct
If no legal, regulatory, contractual, competitive, economic, or other factors limit the life of an intangible asset, the asset's assigned value is allocated to the expense Indefinitely (no amortization= depreciation of intangible assets like patent rights, copy rights,etc.) with an annual impairment review until its life becomes finite.
Answer: strategy
Explanation:
The functions of management can be performed best when a firm's strategy and culture are integrated.
A strategy has to do with the actions and the decisions that a particular organization or business will have to take in order for the organization to be able to accomplish its reach its goals, maximize profit and also be competitive.
Answer:
Internal Rate of Return (IRR) = 10%
Explanation:
The computation of IRR for the new production system is shown below:-
PV factor for Internal Rate of Return = Investment cost ÷ Annual net cash savings
PV factor for Internal Rate of Return = $4,607,200 ÷ $800,000
= 5.759
The PV factor 5.759 in Present value of a Annuity of $1 table for 9 years is closest to 10%
Internal Rate of Return (IRR) = 10%
The the total fixed cost (tfc) of the firm when it produces 1 (one) unit of output will be $15
When Q = 1, TFC = $ 15
Note: TC = FC +VC At Q =3, FC = $ 15. The FC remains constant
Total fixed cost (TFC) is the cost that is constant regardless of the output level. For instance, depreciation, rent, wages, insurance, etc.
Both total fixed costs and total variable costs are included in total costs. The total of a company's fixed costs is the sum of all recurring, non-variable costs. Consider a business that pays $10,000 a month to lease office space, $5,000 a month to rent equipment, and $1,000 a month for utilities. The total fixed costs for the business in this scenario would be $16,000.
To learn more about Total fixed cost click here:
brainly.com/question/16749519
#SPJ4
Answer:
The total overhead variance is $1,095
Explanation:
The total standard overhead cost = Standard hours allowed for the work done x predetermined overhead rate = 21,900 x $5.85 = $128,115
The overhead variance = The total standard overhead cost – The actual overhead cost = $129,210 - $128,115 = $1,095