I believe the answer is: corporate partners
Corporate partners refers to the entity that separated from our organzation, but involved in a cooperation with our organziation in order to achieve a common goal. Corporate partnerships allow the combination of resources that allow more than one company to improve its overall efficiency.
Answer:
(a) Operating activity
(b) Financing activity
(c) Operating activity
(d) Investing activity
Explanation:
Basically there are three types of activities:
1. Operating activities: It includes those transactions which affect the working capital, and it records transactions of cash receipts and cash payments.
2. Investing activities: It records those activities which include purchase and sale of the fixed assets
3. Financing activities: It records those activities which affect the long term liability and shareholder equity balance.
So,
(a) Increase in accounts receivable come under the operating activities, and this is to be in a negative amount
(b) Issue of preference shares comes under financing activity, and this is added while computing the financing activities
(c) The depreciation expenses are added in the net income whereas the bond premium amortization is to be deducted from the net income. These both items have come under operating activities
(d) An increase in land value comes under the investing activity.
Answer:
A. Chip performance per dollar doubles every eighteen months.
Answer:
Comparing plan against actual
Explanation:
The process of project monitoring system formation involves determining: type data to collect, how, when, and who will collect the data, how to analyze the data and how to report current progress to management.
Control in project control is the process of comparing the real value or performance against plan to identify deviations, evaluate possible alternative courses of actions e.t.c.
Project control steps for measuring and evaluating project performance includes:
1. Setting a baseline plan
2. Measuring progress and performance
3. Comparing plan against actual
4. Taking action
In Comparing Plan against Actual in control process, it is vital to measure deviations from plan and entails timely monitoring and measuring the status of the project gives ro for comparisons of actual versus expected plans.Taking Action simply if the deviations from plans are significant, corrective approach is used to bring the project back in line with the original plan.