1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
SOVA2 [1]
3 years ago
5

Your project to obtain charitable donations is now 33 days into a planned 43-day project. The project is divided into 3 activiti

es. The first activity is designed to solicit individual donations. It is scheduled to run the first 28 days of the project and to bring in $26,000. Even though we are 33 days into the project, we still see that we have only 91 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 33 days starting on day 5 and extending through day 38. We estimate that even though we should have (28/33) 85 percent of this activity complete, it is actually only 54 percent complete. This part of the project was scheduled to bring in $151,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $52,000. So far $174,000 has actually been brought in on the project.
Business
1 answer:
lord [1]3 years ago
6 0

Answer:

The question has some details missing ; it continues by saying;  Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.)

Explanation:

  • Let the three activities be 1, 2 and 3 respectively.

  • Firstly, we compute the budgeted revenue of the project till the 33rd day. In other to do this, we need to compute budgeted revenue of each activity.

  • Hence, Budgeted revenue of work completed for Activity 1= Budgeted revenue X Planned completion till date

  • = 26000 X 100% = $26000

Budgeted revenue of work completed for Activity 2= Budgeted revenue X Planned completion till date

  • = 151000 X 85% = $128350

Budgeted revenue of work completed for Activity 3= Budgeted revenue X Planned completion till date

  • = 52000 X 0% = 0

Thus, budgeted revenue of the project = Budgeted rev. of Activity 1 + Budgeted rev. of Activity 2 + Budgeted rev. of Activity 3

  • = 26000 + 128350 + 0 = $154350

Budgeted revenue of work performed till 33rd day,

Budgeted revenue of work performed for Activity 1 = Budgeted revenue X actual completion date

= 26000 X 91% = $23660

Budgeted revenue of work performed for Activity 2= Budgeted revenue X actual completion date

= 151000 X 54% = $81540

Budgeted revenue for work performed for Activity 3 = Budgeted revenue X actual completion date

= 52000 X 0% = $0

Thus, budgeted revenue of work performed project = Budgeted rev. of Activity 1 + Budgeted rev. of  Activity 2 + Budgeted rev. of  Activity 3

= 23660 + 81540 + 0 = $105,200

Schedule variance = Budgeted revenue of work performed - budgeted revenue of work scheduled = 105200 - 154350 = - $49150

The values gotten is an indication that the project is behind schedule.

Schedule performance index = Budgeted revenue of work performed/ budgeted revenue of work scheduled = 105200 / 154350 = 0.6816

A scheduled performance index of less than 1 also indicates project is behind schedule.

Cost variance = Budgeted revenue of work performed - Actual revenue = 105200 -174000 = -$68800

Cost performance index = Budgeted revenue of work performed / Actual revenue = 105200/ 174000 = 0.6046

A cost performance index of less than 1 also indicates project is performing better than planned performance in terms of revenue

You might be interested in
Imagine that a local water company issued $10,000 ten-year bond at an interest rate of 6%. You are thinking about buying this bo
mylen [45]

Answer:

Explanation:

The $10,000 is the face value of the bond. Using a financial calculator, input the following to calculate the price at a year before maturity; i.e. at year 9;

Time to maturity; N = 10 - 9 = 1

Annual interest rate; I/Y = 9%

Annual coupon payment; PMT = 0

Face value of the bond; FV = 10,000

then compute present value ; CPT PV = $9,174.31

Therefore, you will pay less than $10,000 for the bond and the price would be  as above $9,174.31

6 0
3 years ago
Shoshanna, the regional manager of a global sales organization, gives freedom to the sales representatives on the amount spent o
Citrus2011 [14]

Answer:

C. Ethical Standards

Explanation:

The ethical standards establish the parameters of behavior that owners and top executives expect from employees and also from suppliers, at least to the extent of their relationship with the organization.

3 0
3 years ago
A business pays weekly salaries of $30,000 on Friday for a five-day week ending on that day. The adjusting entry necessary at th
algol [13]

Answer:

debit Salaries and Wages Expense, $24,000; credit Salaries and Wages Payable, $24,000.

Explanation:

The journal entry is shown below:

Salaries and Wages Expense A/c Dr $24,000

   To Salaries and Wages Payable $24,000

(Being salary and wages is adjusted)

The computation is shown below:

Five day salary = $30,000

Per day salary = $30,000 ÷ 5 days = $6,000

Now Monday to Thursday salary i.e 4 days salary = $6,000 × 4 days = $24,000

3 0
3 years ago
In​ 1916, the ford motor company sold​ 500,000 model t fords at a price of​ $440. henry ford believed that he could increase sal
quester [9]
For the answer to the question above,
we must use this formula,
(New - Old)/ (Ave. of New and Old)

In this case,
501k -500k/(500,500(which is the ave. of the two.
Then it would be 1k/500,500

Then the answer would be .0020
Then
-1.439.5/439.5 because this is the average of the two.
so the answer would be .0023

Then finally divide the rate on change of quantity by the rate of change in price which is
0.002/-0.0023

Then the answer would be -.87

So the elasticity on the demand of model T is .87 ( remove the negative because elasticity is always positive.)

6 0
3 years ago
Select the correct answer from each drop-down menu.
QveST [7]

Answer:

government's  policy.

Explanation:

Govenment policies on tax decide what to tax and where to allocate the resources of the tax.

7 0
3 years ago
Other questions:
  • At the __________ level of decision making, functional managers focus on monitoring and controlling operational-level activities
    10·1 answer
  • Debit postings to the individual accounts in an accounts receivable subsidiary ledger generally come from the
    10·1 answer
  • The sales strategy of getting at least one additional lead from each person interviewed is called selling deeper.a. Trueb. False
    8·1 answer
  • Why is it important to maintain a career portfolio?
    11·1 answer
  • Why the feedback form is so important for the trainer and the training itself?​
    7·2 answers
  • Part of the budgeting process is summarizing the financial statement effects on the budgeted income statement and the budgeted b
    13·1 answer
  • Foreign investors assess not only the interest rate offered on financial securities but also (check all that apply):
    6·1 answer
  • The Hopper Leg Winery from California's Sonoma Valley is trying to enter the wine market in France. To the company's surprise, i
    11·1 answer
  • Which team role makes treatment decisions and assigns roles.
    7·1 answer
  • Can Eskom raise extra capital for expansion​
    15·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!