Answer:
(C) Yes, most companies allow the responsibility to rest with the requester and the receiver of the material requisition slip.
Explanation:
As Kayleigh is looking over a number of material requisition slips from her employees. She has to sign off on each request after reviewing it, which she thinks is a waste of time and effort. Kayleigh believes that having the name of the employee who requested the materials should be enough. Yes, it is very much true and correct because many companies allow the responsibility to rest with the requester and the receiver of the material requisition slip. Some companies do not want that process to become to become much hectic and lengthy for its management as well as workers. If this process is being followed then less time will be taken to complete the overall project and both the time and cost can be saved to make overall project more effective and efficient as well.
Answer:
Total variable cost if 4 units were produced
= $33.75 x 4 units = $135
Total fixed cost = Total cost - Total variable cost
Total fixed cost = $175 -$135
Total fixed cost = $40
Average fixed cost = Total fixed cost/No of units
Average fixed cost = $40/10 units
Average fixed cost = $4
The correct answer is B
Explanation:
In this case, we need to calculate the total variable cost on the ground that 4 units were produced. Then, we will determine the total fixed cost by deducting the total variable cost from total cost. Finally, we will divide the total fixed cost by 10 units in order to obtain the average fixed cost.
Answer:
The correct option is B.
Explanation:
It is given that Garnett Co. expects to purchase $180,000 of materials in July and $210,000 of materials in August.
Purchase in July = $180,000
Purchase in August = $210,000
Three-fourths of all purchases are paid for in the month of purchase, and the other one-fourth are paid for in the month following the month of purchase.
In August, the cash disbursements for materials purchases be 3/4th of $210,000 (Purchase in August) and 1/4 of $180,000 (Purchase in July).
August's cash disbursements for materials purchases be



The August's cash disbursements for materials purchases be $202500. Therefore the correct option is B.
Answer:
A.$13,000
Explanation:
The computation of ending balance is shown below:-
Factory overhead = $24,000 × 50%
= $12,000
Total cost = Direct material + Direct labor + Factory overhead + Current period cost + Opening work in progress
= $76,000 + $24,000 + $12,000 + $10,000
= $122,000
Ending work in progress = Total cost - Cost of units transferred
= $122,000 - $109,000
= $13,000
Which of these is an example of feedback? C. Asking your supervisor to repeat a set of instructions.