PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
x = 3
Step-by-step explanation:
y = 3 is the equation of a horizontal line parallel to the x- axis.
A line perpendicular to it must therefore be a vertical line parallel to the y- axis with equation
x = c
where c is the value of the x- coordinates the line passes through.
The line passes through (3, 5) with x- coordinate 3 , thus
x = 3 ← equation of perpendicular line
Answer:
6√10
Step-by-step explanation:
factorizing 6 and 60
6 = 2 x 3
60 = 2 x 2 x 3 x 5
hence
√6 · √60
= √ [ (2 x 3) · (2 x 2 x 3 x 5) ]
= √ (2· 2² · 3² · 5)
= √ (2² · 3²) x √(2·5)
= (2 · 3) x √10
= 6√10