Answer:
Variable cost per unit= $2.27 per machine hour
Explanation:
Giving the following information:
January 3,041 $4,032
February 3,456 $4,608
March 4,147 $6,912
April 5,184 $9,101
May 3,686 $5,760
June 5,322 $9,216
To calculate the unitary variable cost, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (9,216 - 4,032) / (5,322 - 3,041)
Variable cost per unit= $2.27 per machine hour
A = $9.99, the amount needed after 1 year
r = 0.018% = 0.00018, interest rate
n = 12, compoundings per year
t = 1, one year duration
Let P = required balance at the beginning of the year.
Then

P(1 + 0.00018/12)¹² = 9.99
1.00018P = 9.99
P = $9.988 ≈ $9.99
Answer: $9.99
Answer:
Explanation:
WORK IN PROCESS INVENTORY
May 1 balance 3770 May 31 Finished Goods 9234
31-May Material 11470
31-May labour 13870
31-May Overheads 9431.6
may 31 Balance 29307.6
JOB COST SHEET
Job no. Beg. WIP Material Labour Overheads Total
430 1340 3850 3400 2312 10902
431 0 4680 8170 5555.6 18405.6
TOTAL 1340 8530 11570 7867.6 29307.6
Note: Total cost of Job 429 transferred to Finished goods:
Beginning cost 2430
Add: Material 2940
Add: Labour 2300
Add: Overheads (2300*68%) 1564
Total cost of Job 429 9234