Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days
Answer:
Irrational
Step-by-step explanation:
Digits that go on forever are irrational if I remeber correctly.
Answer:
D. 7 units
Step-by-step explanation:
Using the formula: A= area a= base 1 b= base 2
H = 2 <u> A </u>
a + b
H = 2 <u> 98 </u>
8 + 20
H = 2<u> 98 </u>
28
H = 2( 3.5)
H = 7
Answer:
And rounded up we have that n=115
Step-by-step explanation:
In order to find the critical value we need to take in count that we are finding the interval for a proportion, so on this case we need to use the z distribution. Since our interval is at 90% of confidence, our significance level would be given by
and
. And the critical value would be given by:
Solution to the problem
The margin of error for the proportion interval is given by this formula:
(a)
The proportion of defectives is estimated as:
. And on this case we have that the margin of error is
and we are interested in order to find the value of n, if we solve n from equation (a) we got:
(b)
And replacing into equation (b) the values from part a we got:
And rounded up we have that n=115