Answer:
<u>$26000</u>
Explanation:
from the question;
check per day; 20000
delay: 3 days
checks to pay suppliers; 17000
clearing time 2 days
<u>we first calculate collection flaot:</u>
collection flaot = average amount of check x outstanding days
= 20000 x 3
= 60000
now we have to calculate <u>disbursements float:</u>
average amount of check x days to clear
= 17000 x 2
= 34000
with these two values we can get the net float
= collection flaot - disbursements float
= 60000 - 34000
= <u>$26000</u>
Answer:
$60,000
Explanation:
The computation of the estimated manufacturing overhead is shown below:
Estimated manufacturing overhead = Direct labor hours × predetermined overhead rate
where,
Direct labor hours = Total Direct labor cost ÷ Cost per hour
= ($100,000 × 75%) ÷ ($5)
= 15,000 direct labor hours
Now the estimated manufacturing overhead equal to
= 15,000 direct labor hours × $4
= $60,000
Answer:
$31.61
Explanation:
In order to determine the amount of interest charged you must first calculate the average daily balance:
average daily balance = [($2,030 x 9) + ($1,450 x 22)] / 31 = $1,618.39
Now we must calculate the daily interest rate:
daily interest rate = 23% / 365 = 0.063%
Finally we multiply the average daily balance times the daily interest rate times the number of days in the billing period:
interest charged = $1,618.39 x 0.063% x 31 days = $31.61