Option answer:
d. Interest = $10.64 and New Balance = $360.64
Answer:
A = $360.64
A = P + I where
P (principal) = $350.00
I (interest) = $10.64
Calculation Steps:
First, convert R as a percent to r as a decimal
r = R/100
r = 1.5/100
r = 0.015 rate per year,
Then solve the equation for A
A = P(1 + r/n)nt
A = 350.00(1 + 0.015/4)(4)(2)
A = 350.00(1 + 0.00375)(8)
A = $360.64
Summary:
The total amount accrued, principal plus interest, with compound interest on a principal of $350.00 at a rate of 1.5% per year compounded 4 times per year over 2 years is $360.64.
The answer is C
“There’s nothing we can do about it”
A,B and D have a positive tone.
But C sounds kinda mean
Answer: $3,086
Explanation:
Wrote checks totaling $41,500 in
October less $39,460 of these checks cleared in October
Wrote checks totaling $45,321 in November less $44,275 cleared the bank in November
Balance of uncleared checks
In October is $41,500 - $39,460 = $2,040
In November is $45,321 - $44,275 = $1,046
Total outstanding checks on 30 Nov is $2,040+$1,046 = $3,086
Answer:
Instructions are listed below
Explanation:
Giving the following information:
The high-low method involves taking the highest level of activity and the lowest level of activity and comparing the total costs at each level.
Mountain has recorded the following for the past nine months:
January:
Number of Cavities= 375
Total cost= $5,300
February:
Number of Cavities 500
TC= 5,850
March
Number of Cavities 350
TC= 5,200
April
Number of Cavities 600
TC=6,250
May
Number of Cavities 325
TC= 5,150
June
Number of Cavities 475
TC= 5,700
July
Number of Cavities 525
TC= 6,100
August
Number of Cavities 575
TC= 6,300
September
Number of Cavities 450
TC= 5,550
A) Variable cost= (Highest activity cost - lowest activity cost) / (Highest activity units - lowest activity units)
Variable cost= (6300 - 5150) / (600 - 325)= 4.18 per unit
Fixed cost= HACost - (variable cost per unit * HAUnits)= 6300 - (4.18*600)= 3792
Fixed cost= LACost - (variable cost per unit* LAUnits)= 5150 - (4.18*325)= 3792
B) Q= 400
Total cost= 3792 + 4.18*400= $5464