Sorry I was moving around taking the picture and my handwriting is sloppy. But I hope you understand how I got the answer
Answer:
the answer would be 7x-8. i hope this helped. :).
Step-by-step explanation:
yepppp
The two linear equations in two variable is:
12 x + 3 y = 40
7 x - 4 y = 38
(a) For a system of equations in two Variable
a x + by = c
p x + q y = r
It will have unique solution , when

As, you can see that in the two equation Provided above

So, we can say the system of equation given here has unique solution.
(b). If point (2.5, -3.4) satisfies both the equations, then it will be solution of the system of equation, otherwise not.
1. 12 x+3 y=40
2. 7 x-4 y=38
Substituting , x= 2.5 , and y= -3.4 in equation (1) and (2),
L.H.S of Equation (1)= 1 2 × 2.5 + 3 × (-3.4)
= 30 -10.20
= 19.80≠ R.H.S that is 40.
Similarly, L H S of equation (2)= 7 × (2.5) - 4 × (-3.4)
= 17.5 +13.6
= 31.1≠R HS that is 38
So, you can Write with 100 % confidence that point (2.5, -3.4) is not a solution of this system of the equation.
Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.