Answer:
It is cheaper to buy the part. The company will save $5,000.
Explanation:
Giving the following information:
UNitary production cost:
Direct Materials $10.50
Direct labor $24.00
Variable factory overhead $ 5.50
Total avoidable Fixed factory overhead= (12*1,000) - 5,000= 7,000
Larson Company has offered to sell 1,000 units of the same part to Scott Corporation for $42 per unit.
First, we need to calculate the total cost of making the units:
Total cost= (10.5 + 24 + 5.5)*1,000 + 7,000= $47,000
Now, the total cost of buying them:
Buy= 1,000*42= $42,000
It is cheaper to buy the part. The company will save $5,000.
Had to look for the options and here is my answer.
How the Federal Reserve could persuade banks to lend out more of their reserves is by REDUCING THE DISCOUNT RATE. The Federal Reserve is known to be the central bank of the United States which regulates the financial activities of the nation and how this affects their economy. Hope this helps.
The act of taking actions that carry out the company's plan is a key part of the control process is a false statement.
<h3>What is the control process?</h3>
The control process is one that entails a carefully act of collecting information in regards to a system, process, as well as person, so as to necessary decisions about them.
Hence, The act of taking actions that carry out the company's plan is a key part of the control process is a false statement.
Learn more about control process from
brainly.com/question/14051119
#SPJ1
Explanation:
1. An annuity is a number of equivalent payments made. For instance, the annuities include daily savings account deposits, monthly home loan payments, monthly insurance and pension payments. Annuity can be defined by the payment dates frequency.
Difference between an ordinary annuity and an annuity due:
In each period certain annuities shall pay the same amount, while varying annuities that differ in amounts. At the end of each time, payments in the standard annuity take place. In comparison, payments for an annuity due are made at the start of the contract.
2. The number of y-axis and discount rate on the x-axis is usually present in an annuity table. Place them on the table for your annuity and then place the cell in which they meet. Multiply the cell number by the amount of money each time is earned.
3. The annuity table contains the amount of contributions you expect to collect at a given interest rate plus a list of equivalent payments. You come to the current value of the payments when you subtract this element by one of the payments. As a quick guide the preceding annuity table includes only figures for discrete intervals and interest rates, which may be not quite the same as a real world scenario.