Answer:
e. $638
Explanation:
payment to be made as per forward contract (IN $)
= 39960/ 1.682
= $23757.43
now the actual rate after 90 days is 1.638
payment at 1.638 rate = 39960/ 1.638
= $24395.6
loss by hedging = $24395.6 - $23757.43
= $638.17
Therefore, The U.S. firm have saved or lost $638 in U.S. dollars by hedging its exchange rate exposure.
Answer:
So the depreciation in year 1 is $95,000
Explanation:
Depreciation is the accounting method that is used to allocate cost of an asset over its useful life. It is assumed that an asset losses values over a period and the salvage or terminal value is the value of the good after its useful life has ended.
Straight line method of depreciation assumes equal allocation of depreciation expense over the useful life of an asset.
In the given the asset value is $570,000 and the terminal value is $0
Using the formula
Depreciation= (Value of asset- Salvage value)/Number of useful years
Depreciation= (570,000-0)/6
Depreciation= $95,000 paid equally for 6 years
So the depreciation in year 1 is $95,000
The project's projected NPV is $185.11. (second option)
<h3>What is the NPV?</h3>
Net present value is the present value of after-tax cash flows from an investment less the amount invested. Only projects with a positive NPV should be accepted.
A project with a negative NPV should not be chosen because it isn't profitable. NPV is calculated by taking the present value of all cash flows over the life of a project. Then, the present value of cash flows is subtracted from the investment's initial investment
NPV = -1200 + 400 / 1.0975 + 425 / 1.0975² + 450 / 1.0975³ + 475 / 1.0975^4
= $185.11
To learn more about net present value, please check: brainly.com/question/25748668
#SPJ1
Answer:
$506,800
Explanation:
The calculation of budgeted materials cost is shown below:-
For computing the budgeted materials cost first we need to find out the total materials for production and materials to be purchased which is here below:-
Total materials for production = Budgeted production × Pounds of raw material per unit
= 35,000 × 4
= 140,000
Materials to be purchased = Total materials for production + Ending raw materials inventory - January 1 inventory
= 140,000 + (39,000 × 4 × 30%) - 42,000
= 140,000 + 46,800 - 42,000
= 186,800 - 42,000
= 144,800
Budgeted materials cost for January = Materials to be purchased × Cost per pound
= 144,800 × $3.50
= $506,800