You have just used the network planning model and found the critical path length is 30 days and the variance of the critical pat

h is 25 days. The probability that the project will be completed in 33 days or less is equal to ______. (2 decimal accuracy)

Mathematics
2 answers:
ollegr [7]3 years ago
6 0

Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .

Step-by-step explanation:

We assume that this is a normally distribution.

Given : The critical path length is 30 days .

i.e. Population mean = \mu=30

Variance : \sigma^2=25

Then, standard deviation : \sigma=\sqrt{25}=5

Z-score :  z=\dfrac{x-\mu}{\sigma}

The value of z corresponding to 33 = z=\dfrac{33-30}{5}=0.6

Now, the p-value = P(x\leq33)=P(z\leq0.6)=0.7257469\approx0.73

Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.

mars1129 [50]3 years ago
4 0

Answer:

0.73

Step-by-step explanation:

A Z-score is a statistical measurement that defines the relationship between a  value and the mean of a group, given the standard deviations from the mean. If a Z score is 0, it implies that that the value being measured is identical to the mean score. A Z-score of 2.0 indicate that  the value being measured is two standard deviation away from the group mean.

Standard deviation = √variance = √25

=5 days

Z value that  corresponding to the possibility of completing the project in 33 days  or less is

Z=(33-30)/5 = 3/5 = 0.6

probability that the project will be completed in 33 days or less = P(Z ≤ 0.6)

from Z table

P(Z ≤ 0.6) = 0.72575 ≈ 0.73  (2 decimal accuracy)

You might be interested in
The slope of the line below is 2. Use the coordinates of the labeled point to find a point-slope equation of the line.
Vanyuwa [196]
Y - 9 = 2(x - 1)

This is because the base equation is below:

y - y1 = m(x - x1)
3 0
3 years ago
a baker starts with 4/10 kilogram. of flour to make bread he adds 3/100 kilogram of flour to his bread mixture how much total fl
Alecsey [184]
43/100 kilograms of flour.
4 0
3 years ago
Read 2 more answers
Could someone help me with 9 problems on my work for geometry? I have attached the document to this question and it's numbers 35
Art [367]

Answer:

yes

Step-by-step explanation:

2=3n=4

8 0
3 years ago
The perimeter of the square can be represented by the expression 36x+44 robin wants to write an equivalent expression for the pe
sukhopar [10]

Answer:

4  (9 x + 11) is an equivalent expression for the perimeter that shows the side length of the square is  (9 x + 11).

Step-by-step explanation:

Here, given The perimeter of the square  = (36 x+44)

Now,as we know :

PERIMETER OF SQUARE = 4 x ( SIDES)

Simplifying the perimeter expression.

Take 4 common out of the expression (36 x+44), we get:

(36 x+44) =  4 (9 x + 11)

⇒ Perimeter of the square  =  4 x  (9 x + 11)

⇒4 x ( SIDES) = 4 x (9 x + 11)

⇒ Each Side = (9 x + 11)

Hence, 4 x (9 x + 11) is an equivalent expression for the perimeter that shows the side length of the square is  (9 x + 11).

5 0
3 years ago
The candy jar has 251 pieces of candy. Sophia adds 31 pieces of candy to it. If the candy is divided equally between 6 campers,
NeTakaya

Answer:

47

Step-by-step explanation:

251+31= 282

282 divided by six = 47

4 0
3 years ago
Read 2 more answers
Other questions:
  • HELP WITH WORD PROBLEM - The quality control engineer of top notch tool company finds flaws in 8 of 60 wrenches examined. Predic
    9·1 answer
  • Charlie wants to order lunch for his friends. He'll order sandwiches and a $2 kid's meal for his little brother. Charlie has $32
    15·2 answers
  • An upright cylindrical tank with radius 8 m is being filled with water at a rate of 2 m3/min. How fast is the height of the wate
    12·1 answer
  • Find the value of the variables in each figure. Explain your reasoning.
    15·1 answer
  • Pam says she will charge 125 plus 15 an hour to paint a house. Michelle will charge $50 plus $20 per hour to paint a house. Afte
    14·1 answer
  • Please help with these six questions! If you can, please answer them all in one comment. Thank you! :) 1. What is the value of t
    8·2 answers
  • Based on the data provided, what is the expected cost of repairs over two years if each repair costs $60?
    9·2 answers
  • The reciprocal of (x-y) is z . If z = 11 , y = -3 then what is the value of x
    8·1 answer
  • Circle O has a circumference of 367 cm
    10·2 answers
  • 4 months to 8 years in ratio
    11·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!