Answer:
Total factory overhead to be charged to each unit of Hooks is $33
Explanation:
Sum of all Activity Cost = Total Factory Overhead
Calculate the total factory overhead to be charged to each unit of Hooks
Activity rate = Budgeted amount / Total of each activity base
∴ Activity Rate
For Setups = 60,000 / 20,000 = 3 per setup
For Inspections = 120,000 / 24,000 = 5 per inspections
For Assembly = 420,000 / 28,000 = 15 per dlh
Activity Cost = Activity base for each unit * Activity rate
∴ Activity Cost
For Setups = 1 x 3 = $3
For Inspections = 3 x 5 = $15
For Assembly = 1 x 15 = $15
Recall that;
Sum of all Activity Cost is the Total Factory Overhead
= $3 + $15 + $15
= $33
A credit card issuer is an unsecured creditor and makes money by imposing charges and fees for transactions one performs to transact via a credit card.
<h3>What is a credit card issuer?</h3>
Credit card issuer is the one who offers such credit facility to the consumer over the credibility of the holder in the market. He is an unsecured creditor, as no collateral is recoverable in case of default by cardholder.
A few ways in which card issuer make money on their cards are as follows:
- Charging interest for late payments of credit amount
- Charging a fee to merchants for accepting payments via cards
- Payment gateway fees
- Charges on withdrawal of cash
Hence, the ways in which a credit card issuer or a credit card company earns money is in the ways as aforementioned above.
Learn more about credit cards issuer here:
brainly.com/question/1160037
<u>Answer:</u> 2minutes
<u>Explanation:</u>
Cycle time is the time between the starting and completion of a process. The average time taken to complete in between the process is the cycle time.
Given
No of units produced = 375 El
No of operational hours = 750 minutes
Calculation of cycle time for this assembly line
The formula for cycle time = 1/Throughput rate.
Throughput rate = (Units Produced or Tasks completed)/ Time
=375/750
=0.5
Throughput rate =0.5
cycle time = 1/Throughput rate
=1/0.5
=2 minutes
Answer:
Product Life Cycle Analysis
Explanation:
No. There are times where
some projects are so important that they need to be finished as soon as
possible. You have to make sure that
employees will be compensated for their work when they do so. Make sure that the company follows proper
guidelines in doing overtime.