Answer: b)because near-critical paths could become critical paths with small delays in these activities
Explanation: Program evaluation and review technique(PERT) technique is used for management of the project .The organizing, maintenance,coordination of any task is done by this chart. The non-critical activities need to be observed carefully because they may create near-critical methods which can lead to complexity.
Other options are incorrect because not all activities are equally rather monitoring is done to avoid errors and slack can occur at any path . Small delays can be caused but not complete project can get delayed and there can be risk of complexity rather than being uncompleted.Thus, the correct option is option(b).
Answer:
allows you to see multiple workbooks at once
Explanation:
I got it right on edge 2020
ISO it is an organzation for agreement on internationational of network communication worldwide
OSI is the model for understanding and designing a network architecture
<span>What can give working people information about their fields, including conferences and leadership opportunities in those fields?
C: a professional organization </span>