Answer:
- $33,678.21
Explanation:
Cash flow Summary of the Project will be as follows
Year 0 = $410,000 + $3,000 = - $413,000
Year 1 = $101,000
Year 2 = $101,000
Year 3 = $101,000
Year 4 = $101,000
Year 5 = $101,000 + $41,000 + 3,000 = $145,000
So the Net Present Value can now be calculated using the CFj function of a Financial calculator as follows :
- $413,000 CF 0
$101,000 CF 1
$101,000 CF 2
$101,000 CF 3
$101,000 CF 4
$145,000 CF 5
i/yr = 13%
Shift NPV = - $33,678.21
Answer:
In a static storage area each product is assigned a specific area, whereas in dynamic storage, product locations and fluid and as such are subject to change.
Answer:
Adjusted Bank Balance = $85,000
Explanation:
Adjustment of bank balance is a bank reconciliation procedure, that is used to match the amount in the bank statement with the amount in the company's balance sheet.
To adjust the bank balance, particulars that need to be subtracted or added to the bank statement balance has to be identified and treated accordingly.
For this example, the adjusted balance is calculated thus:
Adjusted bank balance = (Bank statement balance) - (outstanding checks) +(deposit in transit)
Adjusted Bank Balance = 78,000 - 2,400 + 9,400 = $85,000
Note:
outstanding checks are subtracted because they are payments to be made made by the company, representing a liability to the company (payer)
deposit in transit is an income to the company that has not been credited yet, but that will be credited.
The pdca cycle is a powerful approach for problem solving as it provides the foundation for teams to figure out ways to change and implement new ideas within their group setting and project or business. The PDCA stands for plan-do-check-act. In the planning stage your team will plan by determining what the problem is and what ways to fix it. In the do stage, your team will act on the ways you can solve the problem. In the check stage you are looking to check your work and see what worked and what needs to be changed. The final stage is the act stage which if you find solutions that work, implement them moving forward.
Answer: The options are given below:
A. $292,000
B. $267,250
C. $205,250
D. $275,250
The answer is D. $275,250
Explanation:
Net profit = 425,000 - 338,000 = $87,000
Common Stock =110,000 + 25,000 = $135000
Retained Earnings = 70,000 + 87,000 = $157000
Less: Dividend paid = -$16,750
We will calculate shareholders equity as follows:
Total shareholders' Equity = common stock + retained earnings - dividend paid
=> $135000 + $157000 - $16,750
= $275,250