Answer:
Wilkens' days in inventory for 2017 = 60.833
Explanation:
Given:
Sales = $1,800,000
Beginning inventory = $160,000
Ending inventory = $240,000
Gross profit = $600,000
Inventory turnover = 6 times
Wilkens' days in inventory for 2017 = ?
Computation of Wilkens' days in inventory for 2017:
Wilkens' days in inventory for 2017 = Number of days in a year / Inventory turnover
Wilkens' days in inventory for 2017 = 365 / 6 times
Wilkens' days in inventory for 2017 = 60.833
Answer:
$2914
Explanation:
The following steps would be taken to determine the answer
1. Calculate depreciation expense given the initial information
2. calculate the accumulated depreciation by the second year. Accumulated depreciation is sum of depreciation expense
3. subtract the accumulated depreciation from the cost price of the asset. This would give the book value
4. calculate the depreciation expense using the new information and the book value
Straight line depreciation expense = (Cost of asset - Salvage value) / useful life
($9,920 - $1240) / 5 = $1736
Accumulated depreciation = 1736 x 2 = $3472
Book value at the beginning of 2021 = 9920 - 3472 = $6448
Depreciation expense in 2021 = (6448 - 620) / 2 = $2914
Answer:
b. The slope of the budget constraint is the same for each woman.
Explanation:
Budget Line is the combination of two goods that a consumer can buy, given prices & money income (all spent).
Equation : p1x1 + p2x2 = m ;
where p1 & p2 are price of good 1 & 2 , x1 & x2 are quantities of good 1 & good 2 , m = money income
- Abby's Budget Line : 5I + 8N = 80
- Bobbi's Budget Line : 5I + 8N = 60
- Deborah's Budget Line : 5I + 8N = 40 [ I = Icecream, N = Novel ]
Slope of Budget Line represents change (sacrifise) of a good needed to get change (gain) of other good, given same prices & income.
Slope = ΔY/ΔX = Px / Py
Since prices are same for each woman, price ratios & hence the slope of budget line will also be same for all of them.
As a project nears is completion, it has been found that it becomes a significant challenge to get the project team to remain focused.
<h3>Why does focus reduce as a project nears completion?</h3>
There are several reasons why a project nearing completion would lead to a loss of focus and one of them fatigue from having worked on the project for a certain period of time.
Another reason is that the project team will be getting ready to move onto a new project as the current project comes to an end. As a result, they will focus less on the current project.
In conclusion, teams lose focus as their project nears completion.
Options for this question are:
- focused
- working
- energetic
- together
- performing
Find out more on project teams at brainly.com/question/13321211
#SPJ1
Answer:
The correct answer is
c. Reduced job satisfaction
good luck