Answer:
The stock price is 38.63
Explanation:
We use the gordon model to calculate the horizon value and with htat the value of the stock:

D1 = 2.60 x 1.04 = 2.704
rate of return 11% = 0.11
grow rate = 4% = 0.04

P0 = 38.62857143
The taxes should be ignored as the gordon model do not include them in the calculations
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
decreases
Explanation:
When bonds are sold at a premium, it is sold at a price higher than the par value. For example, if the par value is $100, the bond would be selling at a premium if it is sold at $101. At expiration of the bond's tenor, the price of the bond must equal its par value, so at each each interest payment day, the interest expense decreases
Answer:
The correct answer is option c.
Explanation:
Forlornistan is experiencing an economic downturn, the GDP has steadily declined, the employment rate is very low and the CPI is falling.
All these characteristics show that the economy is going through economic depression.
Depression refers to the situation in which an economy suffers a downturn in economic activities. It involves decrease in output level, price and employment rate.
Answer:
Afghntyjnytnjtyjnmtymtumtumumyumyumjm
Explanation: