Answer:
Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.
Shrink nations work force
The equivalent units for the month for the first department for material is 48,000 and for labor and overhead 46000.
What is the weighted average ?
- One of three methods for valuing the stock in your company's inventory is the weighted average cost method, which establishes the average cost of all the products in your inventory based on their individual costs and the quantity of each item that is kept on hand.
- The weighted average is used by businesses to calculate the amount that goes into inventory and the cost of products sold (COGS).
- Due to the variety of inventory stock kinds or the same stock items being purchased at various times, a firm may pay varying costs when purchasing pieces of inventory.
Total units transferred = 42000
and, units of ending WIP = 6000(material), 4000(Labor), 4000(overhead)
So,
Equivalent units of production = 48000(material), 46000(Labor), 46000(overhead)
The equivalent units for the month for the first department for material is 48,000 and for labor and overhead 46000.
Learn more about weighted average here:
brainly.com/question/16557719
#SPJ4
Answer:
The correct answer is D.
Explanation:
Giving the following information:
Total Cost Production (units)
April $119,400 281,300
May 92,000 162,800
June 99,000 238,000
<u>To calculate the variable cost per unit and the total fixed cost, we need to use the following formula:</u>
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (119,400 - 92,000) / (281,300 - 162,800)
Variable cost per unit= $0.231
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 119,400 - (0.231*281,300)
Fixed costs= $54,701