There are several features of business intelligence. It is a content-free expression, which means that it means different things to different people, and not same thing as suggested by Option B. While its major objective is to enable or allow easy access to data, it is not limited to data and IT only as suggested by Option C. Instead it provides managers of businesses with the ability of analysis of data. And finally it helps in the transformation of data to information and to action, which is contrary to the suggestions of Option D. Hence the first option is the only correct option.
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.
Answer:
For most space objects, we use light-years to describe their distance. A light-year is the distance light travels in one Earth year. One light-year is about 6 trillion miles (9 trillion km). That is a 6 with 12 zeros behind it!
<span>Ensure that at </span>least one<span> writable </span>DC<span> must be running </span>Windows Server 2008<span> or higher before you can deploy a Read-Only-Domain-Controller.</span>
Answer:
system software is the software which control overall operation of the computer . For eg. Ms.dos ,window 2003 ,etc whereas application software is a software which work on the top of operating system to solve number of problems .For eg. Ms.word,Ms.excel,etc