Answer:
To determine the current equivalent cost of a construction built in 1980 whose cost was $ 2.7 million, we must establish the relationship between the price index for that year, comparing it with that of the current year.
Taking into account that the average cost index for 1980 was 1941, and that said value is currently 3620, we can note that there was a significant increase in costs. Since 3620/1941 = 1.86, to determine the current cost of construction we must multiply its cost by 1.86.
So, since 2.7 x 1.86 = 5.022, we can establish that the equivalent cost at current prices of said building would have been $ 5,022,000.
Answer: I would choose the 3rd choice.
Explanation:the creation of privately-owned businesses
Answer:
Average time per unit is 59.6 hours
Explanation:
As we know as the work is done the learning of the labor force increases and they require less time to produce the next unit. An average time required to produce specific numbers of unit including cumulative effect of the learning curve.
As per given data
Number of units = 30 unit
Ratio of Time to produce second unit = 90 / 100 = 0.9
Accumulated Average time per unit Formula is
y = aX^b
Where
y = Average time per unit = ?
X = Cumulative Numbers of unit = 30
a = Time required to produce first unit = 100 hours
b = factor used to calculate cumulative average time = log (Learning Curve %/ log2) = Log (90/100) / Log2 = -0.152
Place value value in the formula
y = 100 x 30^ -0.152 = 59.6 hours
Answer:
I use coffee daily. The supply for the coffee I bought (Colombian Coffee) is few then the price is expensive. As the price is expensive I can only buy 2 pounds of this item per month. My demand is affected for the price that producers set to this coffee. I would like to buy more but then the supply of this product is limited therefore the prices will always be high.
Convert Hours per shift into total days worked for a week then convert it into total 365 - Days working + Hourly Pay