Answer:
I exactly don't know the answer
Answer:
It will take you 0.24 hour to ride to your grandparents’ home
It will take you 14 minutes to ride to your grandparents’ home
Step-by-step explanation:
- Your average speed is 15 miles per hour
- The distance to grandmother home is 3.67 miles
- You need to know how long it will take you to do that
∵ Distance = speed × time
∵ Distance = 3.67 miles
∵ Speed = 15 miles per hour
- Substitute these values in the rule above
∴ 3.67 = 15 × time
- Divide both sides by 15 to find the time
∴ Time = 0.24 hour
* It will take you 0.24 hour to ride to your grandparents’ home
- You need to convert the time from hour to minutes
∵ 1 hour = 60 minutes
∵ Time = 0.24 hour
∴ Time = 0.24 × 60 = 14.4
∴ Time ≅ 14 minutes
* It will take you 14 minutes to ride to your grandparents’ home
Hello :
<span>f(x) = 4x − 5 and g(x) = 3x + 9
</span><span>(f + g)(x) = f(x) +g(x) = (4x-5) +(3x+9)
</span><span>(f + g)(x) =7x +4
</span><span>(f ⋅ g)(x) = f(x) × g(x) = (4x-5)(3x+9) = 12x² +36x -15x-45
</span>(f ⋅ g)(x) = 12x² +21x -45
<span>f[g(x)] = f(3x+9) = 4(3x+9) -5
</span><span>f[g(x)] = 12x +31</span>
Answer:P(x<10) =0
Step-by-step explanation:
M =1/μ
M= 1/15 =0.066667
X- Exp (0.066667)
Where: X is the random variable for number of days
P (X<x) = 1 - e^-mx
P(X - x) = 1 - e^-0.06666 x10
P(x<10) = 0
Answer:
Expected return for site A = $9.6 million
Expected return for site B = $12.4 million
according to the above results the company should choose SITE B because it has higher Expected return
Step-by-step explanation:
Given;
For site A,
Site A net if successful = $30 million
Success probability = 0.4
Site A loss if not successful= -$4 million
Probability of not successful = 0.6
For site B.
Site B net if successful = $60 million
Success probability = 0.3
Site B loss if not successful= -$8 million
Probability of not successful = 0.7
To estimate the expected return on an event with outcomes X1 and X2 with probabilities p1 and p2
E = X1(p1) + X2(p2)
Substituting for site A
E = 30(0.4) - 4(0.6)
E = $9.6 million
Substituting for site B
E = 60(0.3) - 8(0.7)
E = $12.4 million
Therefore, according to the above results the company should choose site B because it has higher Expected return